[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939602":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939602,606,2,"多选题","工程项目管理团队内部各部门的要求和期望包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","优良的工作环境",true,{"key":16,"text":17,"correct":14},"B","松弛的工作进度表",{"key":19,"text":20,"correct":21},"C","投资较高",false,{"key":23,"text":24,"correct":21},"D","无社会风险",{"key":26,"text":27,"correct":14},"E","有足够的人力资源","ABE","本题考查的是工程项目的主要利益相关方及其要求和期望。内部各部门的要求和期望包括：松弛的工作进度表，优良的工作环境，有足够信息资源、人力资源和物资资源。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]