[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939601":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939601,606,2,"多选题","WBS 是通过控制划分工程项目单元的（ ）目标来达到控制整个工程项目的目的。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","质量",true,{"key":16,"text":17,"correct":14},"B","费用",{"key":19,"text":20,"correct":14},"C","进度",{"key":22,"text":23,"correct":24},"D","合同",false,{"key":26,"text":27,"correct":24},"E","安全","ABC","本题考查的是工程项目的系统管理原理。WBS 是—种层次化的树状结构，是将工程项目划分为可以管理的工程项目单元，通过控制这些单元的费用.进度和质量目标，达到控制整个工程项目的目的。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]