[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939595,606,1,"单选题","项目阶段划分的数量和必要性及每个阶段所需的控制程度取决于若干因素，下列不属于该因素的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目的功能",true,{"key":16,"text":17,"correct":18},"B","项目的规模",false,{"key":20,"text":21,"correct":18},"C","项目的复杂程度",{"key":23,"text":24,"correct":18},"D","项目的潜在影响","本题考查的是工程项目周期及阶段划分。阶段划分的数量和必要性及每个阶段所需的控制程度，取决于项目的规模、复杂程度和潜在影响",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]