[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939587":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939587,606,2,"多选题","关于工程项目管理模式说法，正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","管理模式的选择是项目准备阶段的重要工作之一",false,{"key":16,"text":17,"correct":14},"B","工程项目投资建设的基本组织模式决定了管理模式",{"key":19,"text":20,"correct":21},"C","项目管理模式规定了合同关系",true,{"key":23,"text":24,"correct":21},"D","项目管理模式规定了项目完成后的运营方式",{"key":26,"text":27,"correct":21},"E","项目管理模式确定了项目参与方的风险分担","CDE","本题考查的是工程项目业主方管理模式。选项 A 错误，管理模式的选择是项目策划阶段的重要工作之一；选项 B 错误，工程项目管理模式的决定因素是多方面的。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]