[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939586":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939586,606,2,"多选题","过程管理采用 PDCA 循环的动态管理模式，通过循环管理达到以下目的（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","选择最佳路径",true,{"key":16,"text":17,"correct":14},"B","确定过程有效运行条件、控制关键点和方法",{"key":19,"text":20,"correct":14},"C","界定过程间的接口",{"key":22,"text":23,"correct":24},"D","改变各过程活动",false,{"key":26,"text":27,"correct":14},"E","确保持续改进","ABCE","本题考查的是工程项目管理的基本原理。通过循环管理达到以下目的：选择最佳路径；确定过程有效运行条件、控制关键点和方法；明确各过程的联系，界定过程间的接口；协调各过程活动；确定监视、测量、分析过程的方法和步骤；确保持续改进。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]