[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939581":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939581,606,2,"多选题","咨询部门的要求和期望包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","优厚的利润",false,{"key":16,"text":17,"correct":18},"B","松弛的工作进度表",true,{"key":20,"text":21,"correct":14},"C","及时提供施工图纸",{"key":23,"text":24,"correct":14},"D","最小限度的变动",{"key":26,"text":27,"correct":18},"E","迅速提供信息","BE","本题考查的是工程项目的主要利益相关方及其要求和期望。咨询、勘察设计等部门的要求和期望：合理的报酬，松弛的工作进度表，迅速提供信息，迅速决策，按时支付工作报酬",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]