[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939573":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939573,606,1,"单选题","工程项目目标系统的建立依据不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","业主的需求说明",false,{"key":16,"text":17,"correct":14},"B","有关法律法规",{"key":19,"text":20,"correct":14},"C","类似项目的历史数据",{"key":22,"text":23,"correct":24},"D","承包商工作经验",true,"本题考查的是工程项目管理的基本原理。工程项目目标系统的建立依据包括：业主的需求说明；国家、地方政府颁布的法律、法规、规章等；国家和行业颁布的强制性标准、规范、规程等；其他资料。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]