[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939571,606,1,"单选题","工程项目目标系统的建立过程中，提出项目目标后应进行的工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","识别需求",false,{"key":16,"text":17,"correct":14},"B","项目构思",{"key":19,"text":20,"correct":21},"C","建立目标系统",true,{"key":23,"text":24,"correct":14},"D","执行项目目标","本题考查的是工程项目管理的基本原理。工程项目目标系统的建立过程中，提出项目目标后应进行的工作是建立目标系统。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]