[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939570":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939570,606,1,"单选题","由于项目管理采用目标管理方法，因此在（ ）过程中就应建立目标系统，并将其贯穿于项目全过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","前期策划",true,{"key":16,"text":17,"correct":18},"B","前期准备",false,{"key":20,"text":21,"correct":18},"C","前期可行性研究",{"key":23,"text":24,"correct":18},"D","项目实施","本题考查的是工程项目管理的基本原理。由于项目管理采用目标管理方法，因此在前期策划过程中就应建立目标系统，并将其贯穿于项目全过程。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]