[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939566,606,1,"单选题","PMBOK中的项目管理的管理过程不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","启动",false,{"key":16,"text":17,"correct":14},"B","计划",{"key":19,"text":20,"correct":21},"C","变更",true,{"key":23,"text":24,"correct":14},"D","执行","本题考查的是国际上常用的工程项目管理知识体系。PMBOK中的项目管理的管理过程包括：启动、计划、执行、控制、收尾。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]