[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939560":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939560,606,2,"多选题","下列项目管理任务中，属于《项目管理知识体系指南(PMBOK)》所述项目管理过程的有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","项目启动",true,{"key":16,"text":17,"correct":14},"B","项目计划",{"key":19,"text":20,"correct":14},"C","项目执行",{"key":22,"text":23,"correct":14},"D","项目控制",{"key":25,"text":26,"correct":27},"E","项目投产运营",false,"ABCD","PMBOK(项目管理知识体系)。项目管理的管理过程，包括启动、计划，执行、控制、收尾。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]