[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939551":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939551,606,2,"多选题","下列工作中，属于工程项目实施阶段的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目征地",false,{"key":16,"text":17,"correct":14},"B","概算编制",{"key":19,"text":20,"correct":21},"C","工程施工",true,{"key":23,"text":24,"correct":21},"D","联动试车",{"key":26,"text":27,"correct":14},"E","生产运营","CD","本题考查的是工程项目各阶段主要工作内容。选项AB为准备阶段工作；选项E为投产运营阶段工作。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]