[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939550,606,1,"单选题","工程项目设计是工程项目（ ）阶段的工作内容。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","策划和决策",false,{"key":16,"text":17,"correct":18},"B","准备",true,{"key":20,"text":21,"correct":14},"C","竣工验收和总结评价",{"key":23,"text":24,"correct":14},"D","实施","本题考查的是工程项目各阶段主要工作内容。工程项目准备阶段主要工作包括：工程项目的初步设计和施工图设计，工程项目征地及建设条件的准备，工程招标并与承包人签订承包合同，获得相关工程建设行政许可，货物采购等。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]