[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939549":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939549,606,1,"单选题","工程项目建设周期中，投入人力、物力、财力最多，管理难度也最大的阶段是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工验收",false,{"key":16,"text":17,"correct":18},"B","实施",true,{"key":20,"text":21,"correct":14},"C","试生产",{"key":23,"text":24,"correct":14},"D","准备","本题考查的是工程项目各阶段主要工作内容。工程项目实施阶段在工程项目建设周期中工作量最大，投入的人力、物力和财力最多，工程项目管理的难度也最大。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]