[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939542":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939542,606,1,"单选题","某工程项目建设周期较长，实施期间项目的建设条件和外部环境发生了变化，这体现了工程项目（ ）的特征。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","复杂性",true,{"key":16,"text":17,"correct":18},"B","—次性",false,{"key":20,"text":21,"correct":18},"C","整体性",{"key":23,"text":24,"correct":18},"D","固定性","本题考查的是工程项目的特征。工程项目特别是大型工程项目，投资建设周期长，影响因素多，有些因素具有不确定性和突发性，后果严重，从而导致工程项目的复杂性。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]