[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939507":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939507,606,2,"多选题","按国家的有关规定，一般工程项目的两个阶段设计包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","方案设计",false,{"key":16,"text":17,"correct":18},"B","初步设计",true,{"key":20,"text":21,"correct":14},"C","技术设计",{"key":23,"text":24,"correct":14},"D","总图设计",{"key":26,"text":27,"correct":18},"E","施工图设计","BE","本题考查的是工程项目设计阶段的安全管理。按照国家的有关规定，一般工程项目按两个阶段进行设计，即初步设计和施工图设计。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]