[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939474,606,1,"单选题","工程项目的安全预评价工作应在项目（ ）完成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初步设计会审前",true,{"key":16,"text":17,"correct":18},"B","项目申请报告核准前",false,{"key":20,"text":21,"correct":18},"C","安全生产许可评审前",{"key":23,"text":24,"correct":18},"D","可行性研究报告报批前","本题考查的是工程项目前期阶段的安全管理。工程项目的安全预评价工作应在工程可行性研究阶段进行。在工程项目初步设计会审前完成，并通过安全监督管理部门的审批。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]