[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939465":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939465,606,1,"单选题","根据《预评价导则》要求，预评价的内容不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","危险度评价",false,{"key":16,"text":17,"correct":14},"B","对策措施及建议",{"key":19,"text":20,"correct":14},"C","危险、有害因素识别",{"key":22,"text":23,"correct":24},"D","工程项目的重大危险源分析",true,"预评价主要包括①危险、有害因素识别，②危险度评价和③对策措施及建 议等方面的内容。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]