[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939438":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939438,606,1,"单选题","工程项目安全预评价是在工程项目的（ ）阶段开展的一项工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可行性研究",true,{"key":16,"text":17,"correct":18},"B","初步设计",false,{"key":20,"text":21,"correct":18},"C","施工",{"key":23,"text":24,"correct":18},"D","竣工验收","本题考查的是工程项目安全管理。工程项目安全预评价是在工程项目的可行性研究阶段开展的一项工作。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]