[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939435":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939435,606,1,"单选题","建立和实施质量管理体系的步骤中，质量管理职能分层次分解之后要做的工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","质量目标层层分解",false,{"key":16,"text":17,"correct":14},"B","制订工程项目的质量计划",{"key":19,"text":20,"correct":21},"C","制订质量管理体系文件",true,{"key":23,"text":24,"correct":14},"D","按质量目标组织实施","本题考查的是工程项目质量管理体系。建立项目质量管理体系的基本方法和步骤：确定项目管理的质量方针和质量目标→把质量目标层层分解→质量管理职能分层次分解→制订质量管理体系文件→制订可操作的质量计划→按质量计划组织实施→持续改进质量管理体系。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]