[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939431":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939431,606,1,"单选题","勘察现场作业的质量管理不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","现场作业人员应进行专业培训",false,{"key":16,"text":17,"correct":14},"B","勘察仪器、设备、试验室有明确的管理程序",{"key":19,"text":20,"correct":14},"C","原始记录表格经有关作业人员检查、签字",{"key":22,"text":23,"correct":24},"D","工程勘察报告完整",true,"本题考查的是勘察阶段质量管理的工作内容。工程勘察报告完整是勘察文件的质量管理要求。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]