[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939428":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939428,606,1,"单选题","施工质量控制流程不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工质量目标制定",true,{"key":16,"text":17,"correct":18},"B","施工质量目标分解",false,{"key":20,"text":21,"correct":18},"C","施工技术交底与工序控制",{"key":23,"text":24,"correct":18},"D","施工质量偏差控制","本题考查的是实施阶段质量管理的工作内容。施工质量控制流程包括下列流程：（1）施工质量目标分解；（2）施工技术交底与工序控制；（3）施工质量偏差控制；（4）产品或服务的验证、评价和防护。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]