[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939426":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939426,606,1,"单选题","单位工程质量验收合格的标准不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","所含分部工程的质量均验收合格",false,{"key":16,"text":17,"correct":14},"B","质量管理资料应完整",{"key":19,"text":20,"correct":21},"C","所含分部工程所有使用功能的检验资料应完整",true,{"key":23,"text":24,"correct":14},"D","观感质量应符合要求","本题考查的是施工质量验收管理的工作内容。所含分部工程中有关安全、节能、环境保护和主要使用功能的检验资料应完整。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]