[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939424":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939424,606,2,"多选题","初步设计阶段，需报政府审批的主要技术文件包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","规划设计方案",false,{"key":16,"text":17,"correct":18},"B","建筑工程初步设计",true,{"key":20,"text":21,"correct":18},"C","建设工程规划许可证",{"key":23,"text":24,"correct":14},"D","人防规划设计",{"key":26,"text":27,"correct":14},"E","交通设计","BC","本题考查的是设计阶段质量管理的工作内容。初步设计阶段，需报政府审批的主要技术文件包括建筑工程初步设计、建设工程规划许可证。 设计各阶段需报政府审批的主要技术文件",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]