[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939422":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939422,606,2,"多选题","主体结构、节能分部工程的验收参加人员包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工单位项目负责人",true,{"key":16,"text":17,"correct":14},"B","施工单位项目技术负责人",{"key":19,"text":20,"correct":21},"C","勘察单位项目负责人",false,{"key":23,"text":24,"correct":14},"D","施工单位技术、质量部门负责人",{"key":26,"text":27,"correct":14},"E","设计单位项目负责人","ABDE","本题考查的是施工质量验收管理的工作内容。分部工程应由总监理工程师组织施工单位项目负责人和项目技术负责人等进行验收。勘察、设计单位项目负责人和施工单位技术、质量部门负责人要参加地基与基础分部工程的验收；设计单位项目负责人和施工单位技术、质量部门负责人要参加主体结构、节能分部工程的验收。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]