[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939418":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939418,606,1,"单选题","《建设工程项目管理规范》对设计质量控制规定了 5 个具体流程，第三个流程是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计策划",false,{"key":16,"text":17,"correct":14},"B","设计输入",{"key":19,"text":20,"correct":21},"C","设计评审",true,{"key":23,"text":24,"correct":14},"D","设计输出","《建设工程项目管理规范》对设计质量控制规定了 5 个具体流程，黑 钻 押 题，金 考 典 软 件 考 前 更 新，下载链接 www.j i n k a o d i a n.c o m 包括：按照设计 合同要求进行设计策划、根据设计需求确定设计输入、实施设计活动并进行设计评审、验证和确 认设计输出和实施设计变更控制。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]