[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939412":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939412,606,2,"多选题","根据《建设工程项目管理规范》相关规定，下列属于项目质量管理实施程序的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定质量计划",true,{"key":16,"text":17,"correct":18},"B","质量计划评审",false,{"key":20,"text":21,"correct":14},"C","实施质量控制",{"key":23,"text":24,"correct":14},"D","落实质量改进",{"key":26,"text":27,"correct":14},"E","开展质量检查与处置","ACDE","本题考查的是实施阶段质量管理的程序和依据。《建设工程项目管理规范》规定，项目质量管理应按下列程序实施：（1）确定质量计划；（2）实施质量控制；（3）开展质量检查与处置；（4）落实质量改进。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]