[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939408,606,1,"单选题","根据《质量管理体系 基础和术语》，在建立质量管理体系时，应该结合（ ），把质量目标层层分解，使工作目标和质量目标相结合。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","质量方针",false,{"key":16,"text":17,"correct":14},"B","质量目标",{"key":19,"text":20,"correct":14},"C","质量计划",{"key":22,"text":23,"correct":24},"D","项目工作分解结构",true,"本题考查的是工程项目质量管理体系和责任体系。建立项目质量管理体系的基本方法和步骤的第二点是：结合项目工作分解结构，把质量目标层层分解，使各项工作目标和质量目标结合起来。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]