[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939407":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939407,606,1,"单选题","PDCA 循环管理法中，P 代表的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","实施行动计划",false,{"key":16,"text":17,"correct":14},"B","评估结果检查",{"key":19,"text":20,"correct":14},"C","质量效益的现值",{"key":22,"text":23,"correct":24},"D","从问题的定义到行动计划",true,"本题考查的是工程项目质量管理的基本方法。P 代表的是计划，即从问题的定义到行动计划。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]