[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939401":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939401,606,1,"单选题","施工图经审查合格后，在设计文件交付施工时，设计单位应当对提交的施工图设计文件 向( )做出详细的说明，进行系统的设计技术交底。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位和监理单位",true,{"key":16,"text":17,"correct":18},"B","施工单位和建设单位",false,{"key":20,"text":21,"correct":18},"C","施工单位和勘察单位",{"key":23,"text":24,"correct":18},"D","建设单位和监理单位","施工图经审查合格后，在设计文件交付施工时，设计单位应当按照法律规定，对提 交的施工图设计文件向施工单位和监理单位做出详细的说明，进行系统的设计技术交底。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]