[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939399":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939399,606,2,"多选题","工程质量管理的三阶段控制法是对质量进行( )",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","事前控制",true,{"key":16,"text":17,"correct":14},"B","事中控制",{"key":19,"text":20,"correct":14},"C","事后控制",{"key":22,"text":23,"correct":24},"D","全面控制",false,{"key":26,"text":27,"correct":24},"E","全过程控制","ABC","三阶段控制法是对质量进行事前控制、事中控制和事后控制。事前进行计划预控， 事中进行自控和监控，事后进行偏差纠正。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]