[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939395":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939395,606,2,"多选题","质量控制点的内容不包括（ ）。 ??",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","隐蔽工程验收",false,{"key":16,"text":17,"correct":18},"B","对下道工序有影响的部位",true,{"key":20,"text":21,"correct":14},"C","影响下道工序质量的技术间歇时间",{"key":23,"text":24,"correct":18},"D","与施工质量有关的参数",{"key":26,"text":27,"correct":14},"E","容易出现质量通病的部位","BD","本题考查的是实施阶段质量管理的工作内容。质量控制点包括下列内容：（1）对施工质量有重要影响的关键质量特性、关键部位或重要影响因素；（2）工艺上有严格要求，对下道工序的活动有重要影响的关键质量特性、部位；（3）严重影响项目质量的材料质量和性能；（4）影响下道工序质量的技术间歇时间；（5）与施工质量密切相关的技术参数；（6）容易出现质量通病的部位；（7）紧缺工程材料、构配件和工程设备或可能对生产安排有严重影响的关键项目；（8）隐蔽工程验收。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]