[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939394":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939394,606,2,"多选题","施工单位的质量责任和义务包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","向建设行政主管部门移交项目档案",false,{"key":16,"text":17,"correct":18},"B","建立质量责任制",true,{"key":20,"text":21,"correct":18},"C","按图施工",{"key":23,"text":24,"correct":14},"D","组织竣工验收",{"key":26,"text":27,"correct":18},"E","现场见证取样送检","BCE","本题考查的是工程项目质量管理责任体系。选项AD均属于建设单位质量责任和义务。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]