[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939387":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939387,606,1,"单选题","（ ）阶段，将设计意图变成工程实体，是保证工程项目质量的关键环节。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程项目前期阶段",false,{"key":16,"text":17,"correct":14},"B","工程项目准备阶段",{"key":19,"text":20,"correct":21},"C","工程项目实施阶段",true,{"key":23,"text":24,"correct":14},"D","工程项目试运行阶段","本题考查的是实施阶段质量管理的程序和依据。实施阶段是将质量目标和质量计划付诸实施的过程，通过施工及相应的质量控制，将设计意图变成工程实体。这一阶段是保证工程项目质量的关键环节。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]