[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939367":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939367,606,1,"单选题","工程勘察工作的三个阶段不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可行性研究勘察",false,{"key":16,"text":17,"correct":14},"B","初步勘察",{"key":19,"text":20,"correct":14},"C","详细勘察",{"key":22,"text":23,"correct":24},"D","施工勘察",true,"工程勘察工作一般分为三个阶段，即可行性研究勘察、初步勘察、详细勘察。工程 地质条件复杂或有特殊施工要求的重要工程，还要进行施工勘察。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]