[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939364":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939364,606,1,"单选题","工程项目质量管理的 PDCA 循环管理法的第三个步骤的内容是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分析现状，找出问题",false,{"key":16,"text":17,"correct":14},"B","分析产生问题的原因",{"key":19,"text":20,"correct":21},"C","主因确认",true,{"key":23,"text":24,"correct":14},"D","制定计划","PDCA 的八个步骤：步骤一：分析现状，找出问题。步骤二：分析产生问题的原因。 步骤三：主因确认。步骤四：制定计划。步骤五：执行措施。步骤六：检查、验证、评估效果。 步骤七：标准化。步骤八：处理遗留问题。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]