[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939360":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939360,606,1,"单选题","工程项目具体质量计划的制订工作不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定影响工程项目质量的因素",true,{"key":16,"text":17,"correct":18},"B","明确项目团队各层次的质量管理职能",false,{"key":20,"text":21,"correct":18},"C","编制收集记录数据的标准表格",{"key":23,"text":24,"correct":18},"D","明确项目团队各层次间的配合和接口","质量计划的内容： ①明确各层次的质量目标和质量管理职能。 ②明确各层次之间的配合和接口。要做到层次清楚、接口明确、结构合理、协调有效。 ③明确实现质量目标的过程顺序，明确过程中进行质量监测的环节和频率以及标准。根据过程控制的原理按过程顺序进行控制，使每个工序都能保证质量。 ④确定和提供实现质量目标必需的资源。 ⑤明确记录和报告数据的标准表格。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]