[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939348":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939348,606,1,"单选题","某工程竣工验收时发现隐蔽工程检査质重不合格，经査，是由于设计缺陷造成的。下列说法中，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计人应负责返修，费用由设计方先行承担",false,{"key":16,"text":17,"correct":14},"B","承包人应负责返修，费用由承包人先行承担",{"key":19,"text":20,"correct":21},"C","承包人应负责返修，费用由发包人先行承担",true,{"key":23,"text":24,"correct":14},"D","由设计缺陷造成质箠不合格的，承包人不负责返修","本题考查的是质量保修期管理的工作内容。建设工程在保修范围和保修期限内发生质量问题的，施工单位应当履行保修义务，并对造成的损失承担赔偿责任。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]