[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939334":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939334,606,2,"多选题","根据中国工程咨询协会《工程咨询成果质量评价办法》，对工业项目可行性研究报告进行风险分析情况综合评价时，需要评价的内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","经营风险分析情况",true,{"key":16,"text":17,"correct":14},"B","管理风险分析情况",{"key":19,"text":20,"correct":21},"C","减少风险分析情况",false,{"key":23,"text":24,"correct":14},"D","财务、金融风险分析情况",{"key":26,"text":27,"correct":14},"E","政策风险分析情况","ABDE","1.经营风险分析情况； 2.管理风险分析情况； 3.财务、金融风险分析情况； 4.政策风险分析情况。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]