[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939328":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939328,606,1,"单选题","某工程项目的计划工期 17 个月，总预算为 3053150 元，项目开工后第 2 个月末的绩效报告表明：计划工作预算费用为 45672 元，已完工作预算费用为 42932 元，已完工作实际费用为 44721 元，假定费用增加趋势不变，则剩余工作的估计费用为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3135655元",true,{"key":16,"text":17,"correct":18},"B","3158912元",false,{"key":20,"text":21,"correct":18},"C","3171806元",{"key":23,"text":24,"correct":18},"D","3180365元","预测的项目完工估算 EAC＝项目完工预算 BAC\u002F费用绩效指数 CPI＝3053150\u002F（42932\u002F44721）＝3180376 元。剩余工作的估计费用＝3180376－44721＝3135655 元。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]