[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939326":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939326,606,1,"单选题","编制工程项目费用计划时，各项工作都按（ ）安排，有利于节约业主方的贷款利息。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最早开始时期",false,{"key":16,"text":17,"correct":14},"B","要求工期",{"key":19,"text":20,"correct":21},"C","最迟开始时期",true,{"key":23,"text":24,"correct":14},"D","计划工期","一般而言，所有工作都按最迟开始时间开始，对节约业主方的建设资金贷款利息是有利的，但同时，也降低了项目按期竣工的保证率。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]