[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939315":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939315,606,1,"单选题","某独立土方工程，招标文件中估计工程量为 100 万 m3，合同中规定：土方工程单价为 10 元\u002Fm3，当实际工程量超过估计工程量 15%时，调整单价，单价调为 9 元\u002Fm3。工程结束时实际完 成土方工程量为 130 万 m3，则土方工程款为( )万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1185",false,{"key":16,"text":17,"correct":14},"B","1125",{"key":19,"text":20,"correct":21},"C","1285",true,{"key":23,"text":24,"correct":14},"D","1385","当应予计算的实际工程量与招标工程量清单出现偏差超过 15%时，对综合单价的调 整原则为：当工程量增加 15%以上时，其增加部分的工程量的综合单价应予调低；当工程量减少 15%以上时，减少后剩余部分的工程量的综合单价应予调高。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]