[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939308":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939308,606,1,"单选题","用（ ）编制设备安装工程概算，计算比较具体，精确性较高。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","扩大单价法",false,{"key":16,"text":17,"correct":14},"B","概算指标法",{"key":19,"text":20,"correct":14},"C","定额单价法",{"key":22,"text":23,"correct":24},"D","预算单价法",true,"本题考查的是设计概算的编制与审查。当初步设计有详细设备清单时，可直接按预算单价（预算定额单价）编制设备安装工程概算。根据计算的设备安装工程量，乘以安装工程预算单价，经汇总求得。用预算单价法编制概算，计算比较具体，精确性较高。 当初步设计的设备清单不完备，或仅有成套设备的重量时，可采用主体设备、成套设备或工艺线的综合扩大安装单价编制概算。 当初步设计的设备清单不完备，或安装预算单价及扩大综合单价不全，无法采用预算单价法和扩大单价法时，可采用概算指标编制概算。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]