[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939306":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939306,606,1,"单选题","市场价格波动引起的价格调整方法不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采用价格指数进行价格调整",false,{"key":16,"text":17,"correct":18},"B","采用第三方调解后确定的价格进行调整",true,{"key":20,"text":21,"correct":14},"C","采用造价信息进行价格调整",{"key":23,"text":24,"correct":14},"D","专用合同条款约定的其他方式","本题考查的是合同价款调整。除专用合同条款另有约定外，市场价格波动超过合同当事人约定的范围，合同价格应当调整。合同当事人可以在专用合同条款中约定选择以下一种方式对合同价格进行调整：（1）采用价格指数进行价格调整；（2）采用造价信息进行价格调整。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]