[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939299":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939299,606,1,"单选题","工程量清单计价中，综合单价的计算步骤中，计算定额子目工程量之后，应进行的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定组合定额子目",false,{"key":16,"text":17,"correct":18},"B","测算人、料、机消耗量",true,{"key":20,"text":21,"correct":14},"C","确定人、料、机单价",{"key":23,"text":24,"correct":14},"D","计算清单项目的人、料、机总费用","本题考查的是工程量清单计价。综合单价的计算可以概括为以下步骤： 1）确定组合定额子目； 2）计算定额子目工程量； 3）测算人、料、机消耗量； 4）确定人、料、机单价； 5）计算清单项目的人、料、机总费用； 6）计算清单项目的管理费和利润； 7）计算清单项目的综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]