[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939298,606,1,"单选题","在工程量清单计价中，其他项目费计算，下列说法不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额和暂估价由招标人按估算金额确定",false,{"key":16,"text":17,"correct":18},"B","暂估价的材料、工程设备和专业工程，经发承包双方协商确认单价后计价",true,{"key":20,"text":21,"correct":14},"C","若专业工程不属于依法必须招标的，由发包人、总承包人与分包人按有关计价依据进行计价",{"key":23,"text":24,"correct":14},"D","计日工和总承包服务费由承包人根据招标人提出的要求，按估算的费用确定","本题考查的是工程量清单计价。暂列金额和暂估价由招标人按估算金额确定。招标人在工程量清单中提供的暂估价的材料、工程设备和专业工程，若属于依法必须招标的，由承包人和招标人共同通过招标确定材料、工程设备单价与专业工程分包价；若材料、工程设备不属于依法必须招标的，经发承包双方协商确认单价后计价；若专业工程不属于依法必须招标的，由发包人、总承包人与分包人按有关计价依据进行计价。计日工和总承包服务费由承包人根据招标人提出的要求，按估算的费用确定。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]