[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939297":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939297,606,1,"单选题","有助于检查各单项工程和单位工程的费用构成是否合理，也可以检查各项具体的费用支出的对象是否明确和落实的费用目标分解方式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投资计划表",false,{"key":16,"text":17,"correct":14},"B","时间－投资累计曲线",{"key":19,"text":20,"correct":14},"C","S形曲线",{"key":22,"text":23,"correct":24},"D","综合分解资金使用计划表",true,"本题考查的是资金使用计划的编制。综合分解资金使用计划表一方面有助于检查各单项工程和单位工程的投资构成是否合理，有无缺陷或重复计算；另一方面也可以检查各项具体的投资支出的对象是否明确和落实，并可校核分解的结果是否正确。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]