[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939296":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939296,606,1,"单选题","当工程量增加15%以上时，其增加部分的工程量的综合单价应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调高",false,{"key":16,"text":17,"correct":18},"B","调低",true,{"key":20,"text":21,"correct":14},"C","不调整",{"key":23,"text":24,"correct":14},"D","协商调整","本题考查的是合同价款调整。当工程量增加15%以上时，其增加部分的工程量的综合单价应调低。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]