[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939294":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939294,606,1,"单选题","施工过程中必须发生，但在投标时很难具体分项预测，又无法单独列出项目内容的措施 项目，措施项目费的计算一般采用( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","综合单价法",false,{"key":16,"text":17,"correct":18},"B","参数法计价",true,{"key":20,"text":21,"correct":14},"C","工料单价法",{"key":23,"text":24,"correct":14},"D","分包法计价","(1)综合单价法。适用于可以计算工程量的措施项目，如混凝土模板、脚手架、垂 直运输等。黑钻押题，金考典软件考前更新，下载链接 www.j inkaodian.com (2)参数法计价。适用于施工过程中必须发生，但在投标时很难具体分项预测，又无法单独 列出项目内容的措施项目。如夜间施工费、二次搬运费、冬雨期施工的计价均可以采用该方法。 (3)分包法计价。适合可以分包的独立项目，如室内空气污染测试等。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]