[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939287,606,1,"单选题","某独立土方工程，招标文件中估计工程量为100万m3，合同中规定：土方工程单价为10元\u002Fm3，当实际工程量超过15%时，单价调为9元\u002Fm3；当实际工程量减少15%时，单价调为11元\u002Fm3。工程结束时，经监理人认可的土方工程量为80万m3，则土方工程款为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","800",false,{"key":16,"text":17,"correct":14},"B","720",{"key":19,"text":20,"correct":21},"C","880",true,{"key":23,"text":24,"correct":14},"D","850","本题考查的是合同价款调整。土方工程款＝80×11＝880（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]